Close Menu

    Closings

    Facebook X (Twitter) Instagram
    • Personalities/Staff
    • Jobs
    • Calendar
    • Contest Rules
    • Contact Us
    • Privacy Policy
    • Login
    RSS Facebook X (Twitter)
    News Radio KMAN
    • Local/State News
      • Manhattan
      • Wamego
      • Riley County
      • Pottawatomie County
      • Fort Riley
      • Geary County
      • State News
      • RCPD Reports
    • Weather
    • Sports
      • K-State Sports
      • High School Sports
        • HS Basketball Schedule & Scores
          • Manhattan High
          • Wamego
          • Rock Creek
          • Riley County
          • Frankfort
          • Blue Valley High
      • Scoreboard Saturday
      • Student-Athlete of the Week
    • Podcasts
      • Within Reason with Mike Matson
      • The Game
      • Wildcat Insider
      • Scoreboard Saturday
    • Obituaries
    • Message Us
      • Birthday/Anniversary
    • Keep It Local
    Listen
    Closings And Delaystyle=
    News Radio KMAN
    You are at:Home»Local News»K-113 from K-18 to U.S. 24 Mill & Overlay Project in Manhattan

    K-113 from K-18 to U.S. 24 Mill & Overlay Project in Manhattan

    0
    By KMAN Staff on April 26, 2017 Local News, Manhattan, Riley County

    On Tuesday, May 2, weather permitting, a 1.5-inch mill and overlay project will begin on a 5.6-mile section of K-113 from K-18 to U.S. 24 in Manhattan. Work will begin on the south end of the project just north of the K-18 Diverging Diamond Interchange Project underway and move north to U.S. 24. Work will take place during daylight hours, Monday through Friday, with some occasional Saturday work.

    Beginning on Tuesday, May 2, northbound and southbound K-113 will be reduced to one open lane each direction for a few miles at a time on the four-lane portion. Traffic will be directed through the project work zone via cones, arrow boards and signage. Traffic will not travel on the milled portion of the K-113 roadway.

    When work advances to the two-lane portion of the roadway, traffic will be reduced to one lane for both directions along with intermittent closures of adjacent cross roads during the project work hours. Drivers should expect delays of up to 15 minutes maximum and are encouraged to use alternate routes, if possible. There will be a 12-foot lane width restriction each direction throughout the project duration.

    Shilling Construction, of Manhattan, is the primary contractor on this $2.044 million preservation project. The project is scheduled to be completed and opened to traffic by July 1, 2017, weather permitting.

    Share. Facebook Twitter Pinterest LinkedIn Tumblr Email
    KMAN Staff
    • Website
    • Facebook
    • X (Twitter)

    Related Posts

    Onaga woman arrested for attempted murder

    Marysville driver injured in K-63 rollover crash

    Police cracking down on CBD products after raid of local store

    Listen Live Here
    Listen Live - Mobile

    Categories

    EEO Report

    FCC Public File

    FCC Applications


    Follow @1350kman on Twitter · Manhattan Broadcasting Company is an equal opportunity employer.
    Manhattan Broadcasting does not discriminate in sale of advertising on the basis of race, gender, or ethnicity, and will not accept advertising which does so discriminate. © 2024 Manhattan Broadcasting Company.

    Follow @1350kman on Twitter · Manhattan Broadcasting Company is an equal opportunity employer.
    Manhattan Broadcasting does not discriminate in sale of advertising on the basis of race, gender, or ethnicity, and will not accept advertising which does so discriminate. © 2024 Manhattan Broadcasting Company.

    Type above and press Enter to search. Press Esc to cancel.