Close Menu

    Closings

    Facebook X (Twitter) Instagram
    • Personalities/Staff
    • Jobs
    • Calendar
    • Contest Rules
    • Contact Us
    • Privacy Policy
    • Login
    RSS Facebook X (Twitter)
    News Radio KMAN
    • Local/State News
      • Manhattan
      • Wamego
      • Riley County
      • Pottawatomie County
      • Fort Riley
      • Geary County
      • State News
      • RCPD Reports
    • Weather
    • Sports
      • K-State Sports
      • High School Sports
        • HS Basketball Schedule & Scores
          • Manhattan High
          • Wamego
          • Rock Creek
          • Riley County
          • Frankfort
          • Blue Valley High
      • Scoreboard Saturday
      • Student-Athlete of the Week
    • Podcasts
      • Within Reason with Mike Matson
      • The Game
      • Wildcat Insider
      • Scoreboard Saturday
    • Obituaries
    • Message Us
      • Birthday/Anniversary
    • Keep It Local
    Listen
    Closings And Delaystyle=
    News Radio KMAN
    You are at:Home»Local News»Manhattan Regional Airport runway reconstruction price tag significantly reduced

    Manhattan Regional Airport runway reconstruction price tag significantly reduced

    0
    By Brandon Peoples on August 11, 2022 Local News, Manhattan
    Manhattan Regional Airport courtesy photo
    Manhattan Regional Airport (KMAN file photo)
    Nine months ahead of a planned major reconstruction of the Manhattan Regional Airport, the cost estimate on the project has been significantly reduced from what it was just a year ago.
    In July 2021, airport officials were looking at a $47 million total project, with the local share estimated around $11 million. Airport officials quickly went to work, finding avenues where costs could be reduced.
    The first step was identifying that concrete could be poured on the rubblized base, using it as a base instead of having a filler. Engineers and staff determined that doing so would still meet FAA requirements. Airport Director Brandon Keazer told Airport Advisory Board members this week that the Federal Aviation Administration (FAA) agreed and approved the airport’s modified plan.
    https://1350kman.com/wp-content/uploads/2022/08/0810-Keazer-3.mp3
    The next step was finding a way to pay for the additional 50 feet of runway not covered by the FAA. Keazer says the airport applied for and was one of the first airports to be awarded a grant through the Defense Community Infrastructure Program (DCIP), pulling down the local share substantially. Keazer says a construction bid from Kansas City-based Clarkson Construction Company came in $16 million, or 38% below the engineer’s estimate. The total project cost is roughly $31 million for construction, with DCIP paying for FAA ineligible items (roughly $3.1 million) and the local share at $3.1 million, which is significantly less than the $11 million estimate from just a year ago.
    https://1350kman.com/wp-content/uploads/2022/08/0810-Keazer-4.mp3
    The project, which will be done in four phases will begin in May and be finished by August 2023.
    Sen. Jerry Moran and Sen. Roger Marshall last month jointly announced a $36 million federal grant had been approved for the project.
    The Airport Advisory Board unanimously supported a resolution to recommend the construction bid to the City Commission, which it’s expected to consider at its Aug. 16 meeting.
    ====
    The full meeting audio from the Aug. 8 meeting is shared below, with Keazer’s presentation starting at around the 17 minute mark. The video presentation of this meeting is available at cityofmhk.com/tv.
    https://1350kman.com/wp-content/uploads/2022/08/0808-Airport-Advisory-Board-Meeting.mp3
    Share. Facebook Twitter Pinterest LinkedIn Tumblr Email
    Brandon Peoples
    • Website

    KMAN News Director and host of In Focus. Contact Brandon at Brandon@1350KMAN.com

    Related Posts

    City commission advances ordinance to establish incentive district for workforce housing

    Amazon expanding to Manhattan after securing purchase agreement

    USD 383 not renewing contract for Bergman Elementary principal

    Listen Live Here
    Listen Live - Mobile

    Categories

    EEO Report

    FCC Public File

    FCC Applications


    Follow @1350kman on Twitter · Manhattan Broadcasting Company is an equal opportunity employer.
    Manhattan Broadcasting does not discriminate in sale of advertising on the basis of race, gender, or ethnicity, and will not accept advertising which does so discriminate. © 2024 Manhattan Broadcasting Company.

    Follow @1350kman on Twitter · Manhattan Broadcasting Company is an equal opportunity employer.
    Manhattan Broadcasting does not discriminate in sale of advertising on the basis of race, gender, or ethnicity, and will not accept advertising which does so discriminate. © 2024 Manhattan Broadcasting Company.

    Type above and press Enter to search. Press Esc to cancel.

    x