Close Menu

    Closings

    Facebook X (Twitter) Instagram
    • Personalities/Staff
    • Jobs
    • Calendar
    • Contest Rules
    • Contact Us
    • Privacy Policy
    • Login
    RSS Facebook X (Twitter)
    News Radio KMAN
    • Local/State News
      • Manhattan
      • Wamego
      • Riley County
      • Pottawatomie County
      • Fort Riley
      • Geary County
      • State News
      • RCPD Reports
    • Weather
    • Sports
      • K-State Sports
      • High School Sports
        • HS Basketball Schedule & Scores
          • Manhattan High
          • Wamego
          • Rock Creek
          • Riley County
          • Frankfort
          • Blue Valley High
      • Scoreboard Saturday
      • Student-Athlete of the Week
    • Podcasts
      • Within Reason with Mike Matson
      • The Game
      • Wildcat Insider
      • Scoreboard Saturday
    • Obituaries
    • Message Us
      • Birthday/Anniversary
    • Keep It Local
    Listen
    Closings And Delaystyle=
    News Radio KMAN
    You are at:Home»Local News»Airport officials inform Advisory Board that runway reconstruction remains on schedule

    Airport officials inform Advisory Board that runway reconstruction remains on schedule

    0
    By Bernie Fancella on September 11, 2023 Local News, Manhattan
    Manhattan Regional Airport courtesy photo

    With less than two weeks to go, Airport Director Brandon Keazer says runway reconstruction is now closing in on being completed in time for American Airlines to begin resuming flights.

    Keazer updated the Airport Advisory Board on the status of the runway project Monday morning. While the current project is officially 3 weeks behind schedule, Keazer says some work has been streamlined in recent weeks to bring the project back on schedule.

    https://1350kman.com/wp-content/uploads/2023/09/0911-Keazer-2.mp3

    American Airlines is scheduled to resume flights Sept. 25.

    The multi million dollar runway reconstruction project has been underway since officials closed the airport in mid-May. Federal grants are covering over $30 million with the city’s share at approximately $3 million.

    Airport Advisory Board Chair Rich Jankovich notes that the runway was originally scheduled to be rebuilt 10 years ago.

    https://1350kman.com/wp-content/uploads/2023/09/0911-Jankovich-1-1.mp3

    Runway 21 center lines, taxi lights, and runway lights are all complete.  A flight check is scheduled for Tuesday at 7 a.m. This will check all instrument approaches, and results will take 24-48 hours as the data will need processed.

    Keazer also provided updates for the taxiways, noting that Taxiway Alpha just needs to be painted and to have lights installed. Taxiway Delta has been removed. Taxiways Echo and Foxtrot have been completed and are ready.

    Keazer also updated the Airport Advisory Board about the upcoming hangar project, noting that designs have been submitted to the FAA and were recently approved. The next step will be bid opening, to take place in November or December. Keazer explains the reason the date to start bids cannot be finalized.

    https://1350kman.com/wp-content/uploads/2023/09/0911-Keazer-1.mp3

    Hangar construction is set to start in Spring 2024, and should complete by Fall 2024 through the end of the year. A total of eight new hangers are included in the project.

     

    Share. Facebook Twitter Pinterest LinkedIn Tumblr Email
    Bernie Fancella
    • Website

    Related Posts

    Hotel evacuated after carbon monoxide leak

    Tornadoes and hail possible as severe storms move in Monday afternoon

    Thunderstorms Expected Across Region Sunday Evening

    Listen Live Here
    Listen Live - Mobile

    Categories

    EEO Report

    FCC Public File

    FCC Applications


    Follow @1350kman on Twitter · Manhattan Broadcasting Company is an equal opportunity employer.
    Manhattan Broadcasting does not discriminate in sale of advertising on the basis of race, gender, or ethnicity, and will not accept advertising which does so discriminate. © 2024 Manhattan Broadcasting Company.

    Follow @1350kman on Twitter · Manhattan Broadcasting Company is an equal opportunity employer.
    Manhattan Broadcasting does not discriminate in sale of advertising on the basis of race, gender, or ethnicity, and will not accept advertising which does so discriminate. © 2024 Manhattan Broadcasting Company.

    Type above and press Enter to search. Press Esc to cancel.

    x