Close Menu

    Closings

    Facebook X (Twitter) Instagram
    • Personalities/Staff
    • Jobs
    • Calendar
    • Contest Rules
    • Contact Us
    • Privacy Policy
    • Login
    RSS Facebook X (Twitter)
    News Radio KMAN
    • Local/State News
      • Manhattan
      • Wamego
      • Riley County
      • Pottawatomie County
      • Fort Riley
      • Geary County
      • State News
      • RCPD Reports
    • Weather
    • Sports
      • K-State Sports
      • High School Sports
        • HS Basketball Schedule & Scores
          • Manhattan High
          • Wamego
          • Rock Creek
          • Riley County
          • Frankfort
          • Blue Valley High
      • Scoreboard Saturday
      • Student-Athlete of the Week
    • Podcasts
      • Within Reason with Mike Matson
      • The Game
      • Wildcat Insider
      • Scoreboard Saturday
    • Obituaries
    • Message Us
      • Birthday/Anniversary
    • Keep It Local
    Listen
    Closings And Delaystyle=
    News Radio KMAN
    You are at:Home»Local News»Riley County approves change order for radio upgrades

    Riley County approves change order for radio upgrades

    0
    By KMAN Staff on October 4, 2019 Local News, Riley County
    Riley County commissioners Ron Wells (left), Marvin Rodriguez (center) and John Ford (right). Sam Hennigh / KMAN

    A change order for the Riley County emergency services radio system upgrade was approved by the Riley County commissioners on Thursday.

    One of the items included in the change order was an expansion to the timeline for completion. Emergency Management Director Pat Collins explained why the project’s completion is being pushed from June 2020 to October 2020.

    “One was that initial six months that they didn’t do anything. The other was the time it took them once we found out the towers indicated in the bid weren’t going to work. We had to go find other towers and locations,” Collins said.

    Collins says the order includes a zero dollar cost that’s been negotiated for and includes $65,000 for a new recorder.

    “I don’t like the wording in the amendment because it looks like we requested it and realistically we did, but it was because the initial tower came with the bid, which failed structural analysis,” he said.

    Testing of the system will begin in April and Collins estimates that will take about a month to complete. He also is optimistic they can complete the project closer to the June date.

    “If there’s some remediation for any of the sites then we’ve got a little bit of time to play with that yet. I really believe that’s a realistic time frame, though I don’t know if we’ll get all the radios installed then, but what I’m worried about is getting that first $5.2 or $6.2 million spent in a time that doesn’t cause us any arbitrage,” Collins said.

    Collins added that Emergency Management will have 30 days after the completion for more rounds of testing to make sure the system is fully operational. He added if this is what is causing a longer delay, then they will be able to complete their own training before completion.

    Another change order will be brought back to the commission at a later date, which amends language in the current contract to add Kansas State University.

    Commissioners meet again on Monday. The agenda includes updates from RCPD and Downtown Manhattan. Riley County Health Department Director Jennifer Green also will discuss Okt-FLU-ber Fest 2019 and efforts the county is taking to ensure the public is getting vaccinated against influenza this season.

    Monday’s meeting begins at 8:30 a.m. in the commission chambers at 115 North 4th Street.

     

    Share. Facebook Twitter Pinterest LinkedIn Tumblr Email
    KMAN Staff
    • Website
    • Facebook
    • X (Twitter)

    Related Posts

    Riley County proposes budget with 17% tax hike for average homeowner

    43-year-old man suffers serious injuries in K-13 crash

    Kentucky men arrested in Junction City after I-70 pursuit, marijuana bust

    Listen Live Here
    Listen Live - Mobile

    Categories

    EEO Report

    FCC Public File

    FCC Applications


    Follow @1350kman on Twitter · Manhattan Broadcasting Company is an equal opportunity employer.
    Manhattan Broadcasting does not discriminate in sale of advertising on the basis of race, gender, or ethnicity, and will not accept advertising which does so discriminate. © 2024 Manhattan Broadcasting Company.

    Follow @1350kman on Twitter · Manhattan Broadcasting Company is an equal opportunity employer.
    Manhattan Broadcasting does not discriminate in sale of advertising on the basis of race, gender, or ethnicity, and will not accept advertising which does so discriminate. © 2024 Manhattan Broadcasting Company.

    Type above and press Enter to search. Press Esc to cancel.