Facebook Twitter Instagram
    • Personalities/Staff
    • Jobs
    • Calendar
    • Keeping it Local
    • Contest Rules
    • Contact Us
    • Login
    RSS Facebook Twitter
    News Radio KMAN
    ESB's Managing Your Money
    • Local/State News
      • Manhattan
      • Riley County
      • Wamego
      • Pottawatomie County
      • Fort Riley
      • Geary County
      • State News
      • RCPD Reports
    • Weather
    • Sports
      • High School Sports
        • Scores
      • Scoreboard Saturday
      • K-State Sports
      • Student-Athlete of the Week
    • On Demand
      • In Focus
      • Who’s On In Focus
      • The Game
      • Managing Your Money by ESB Financial
      • Wildcat Insider
    • Obituaries
    • Message Us
      • Birthday/Anniversary
    Listen
    News Radio KMAN
    You are at:Home»Local News»Delays impacting Pottawatomie County emergency radio system upgrade

    Delays impacting Pottawatomie County emergency radio system upgrade

    0
    By Brandon Peoples on August 30, 2022 Local News, Pottawatomie County
    The Sunflower Room, location of the Pottawatomie County Public Works and KSU Extension offices in Westmoreland. (KMAN file photo)
    Pottawatomie County commissioners received a less than favorable status update Monday to its ongoing radio systems upgrade, that could see delays well into next year.
    Motorola representative Richard Nita told commissioners about supply chain delays for the shipment of generators, which had previously been noted to be around 52-weeks. He says their distributor now expects those to be available by the middle of next summer, at best.
          0829-Nita 1
    It was also noted that shelters for the three tower sites are on a 16-week wait, however Topeka-based TFM Comm, whom Motorola is contracted with, had not placed the order as of Monday. Nita says that should have occurred in April when Motorola presented TFM Comm with a purchase order.
    The company has cited lack of resource availability, likely in staffing. Delays with the contractor could easily push the timeline for completion to November 2023, after having been delayed already once in the process from November 2022 to July 2023. Commissioner Greg Riat says that’s unacceptable.
          0829-Riat 1

    Nita says two suggestions have been brought up, to help speed along the system upgrade, so the project isn’t disrupted further.

          0289-Nita 2

    The second suggestion was to see if another shop could help while TFM Comm is busy. That option has not yet been explored.

    Riat suggested Motorola bump up its anticipated completion date to July 2023, concerned that the rural areas would be jeopardized by inaction.

          0829-Riat 2
    Pottawatomie County is upgrading its communications towers for emergency services in Emmett, Olsburg and Wheaton.

    Share this:

    • Facebook
    • Twitter
    Share. Facebook Twitter Pinterest LinkedIn Tumblr Email
    Brandon Peoples
    • Website

    KMAN News Director and host of In Focus. Contact Brandon at Brandon@1350KMAN.com

    Related Posts

    K-State caterer serves Sunday brunch to help serve the community

    Riley County Commission holds evening meeting in Riley

    Gov. Kelly calls for legislation change at Kansas Governor’s Public Health Conference

    Comments are closed.

    Listen Live Here
    Listen Live - Mobile

    Categories

    EEO Report

    FCC Public File

    FCC Applications


    Follow @1350kman on Twitter · Manhattan Broadcasting Company is an equal opportunity employer.
    Manhattan Broadcasting does not discriminate in sale of advertising on the basis of race, gender, or ethnicity, and will not accept advertising which does so discriminate. © 2022 Manhattan Broadcasting Company.

    Type above and press Enter to search. Press Esc to cancel.