Close Menu

    Closings

    Facebook X (Twitter) Instagram
    • Personalities/Staff
    • Jobs
    • Calendar
    • Contest Rules
    • Contact Us
    • Privacy Policy
    • Login
    RSS Facebook X (Twitter)
    News Radio KMAN
    • Local/State News
      • Manhattan
      • Wamego
      • Riley County
      • Pottawatomie County
      • Fort Riley
      • Geary County
      • State News
      • RCPD Reports
    • Weather
    • Sports
      • K-State Sports
      • High School Sports
        • HS Basketball Schedule & Scores
          • Manhattan High
          • Wamego
          • Rock Creek
          • Riley County
          • Frankfort
          • Blue Valley High
      • Scoreboard Saturday
      • Student-Athlete of the Week
    • Podcasts
      • Within Reason with Mike Matson
      • The Game
      • Wildcat Insider
      • Scoreboard Saturday
    • Obituaries
    • Message Us
      • Birthday/Anniversary
    • Keep It Local
    Listen
    Closings And Delaystyle=
    News Radio KMAN
    You are at:Home»Local News»Manhattan Regional Airport to seek rent abatement for tenants during runway reconstruction

    Manhattan Regional Airport to seek rent abatement for tenants during runway reconstruction

    0
    By Brandon Peoples on March 15, 2023 Local News, Manhattan
    Photo by Brandon Peoples/KMAN

    Manhattan Regional Airport is preparing for its major runway reconstruction this spring, which will include a three month closure of airport services beginning in May.

    The early stages of that project will begin with a temporary closure of the runway between 6 p.m. March 28 and 7 a.m. March 31. Engineer Diane Hofer, with Olsson provided a summary of what’s occurring during Monday’s Airport Advisory Board meeting.

    https://1350kman.com/wp-content/uploads/2023/03/0314-Diane-1.mp3

    She says relocated threshold will be installed and crews will also work to paint numbers and move lights and signs as necessary. Both runways will remain open then from March 31 until May 5, the latter being a week earlier than initially planned.

    https://1350kman.com/wp-content/uploads/2023/03/0314-Diane-2.mp3

    Both runways will be closed between mid-May and mid July, with the final phase of work occurring on runway 3/21 between July 20 and September 1. The airport has shared a complete timeline on its website.

    Airport Director Brandon Keazer says with runway reconstruction and a full closure now less than two months away, he intends to seek rent abatement for airport tenants whose businesses will be disrupted by the project.

    https://1350kman.com/wp-content/uploads/2023/03/0313-BK-2.mp3

    Primary runway affected tenants would include fixed-base operators like the Kansas Jet Center, Heartland Aviation as well as terminal tenants (TSA, Envoy and rental car facilities).

    https://1350kman.com/wp-content/uploads/2023/03/0313-BK-1.mp3

    The Airport Advisory Board unanimously supported the recommendation, which will be presented by Keazer to the Manhattan City Commission at its April 4 meeting.

    In other business Monday, Keazer and Hofer presented plans that are now in place to construct two new hangars at the airport, which is receiving over $2 million in federal money tied to the Bipartisan Infrastructure Law, signed by President Biden in late 2021.

    Keazer says plans are for a 6-bay hangar with stall dimensions of 42′ wide by 33′ deep and a 2-bay hangar that will have a pair of 50′ by 50′ stalls. The grant requires a 10 percent local match, which comes out to about $232,000.

    https://1350kman.com/wp-content/uploads/2023/03/0314-BK-3.mp3

    Keazer says it’s not certain yet what the airport will charge to rent hangar space, but says the goal is to have it cover that local match, noting he intends to work with its engineering firm Olsson on a cost analysis.

    https://1350kman.com/wp-content/uploads/2023/03/0314-BK-4.mp3

    A design agreement will be submitted to the Manhattan City Commission April 4, with construction on the new hangar space expected to begin in spring 2024 and be completed by fall 2024.

     

     

    Share. Facebook Twitter Pinterest LinkedIn Tumblr Email
    Brandon Peoples
    • Website

    KMAN News Director and host of In Focus. Contact Brandon at Brandon@1350KMAN.com

    Related Posts

    City commission rejects Morse nomination to planning board

    Manhattan teen involved in serious crash on US 77

    Manhattan woman arrested after firing gun in road rage incident

    Listen Live Here
    Listen Live - Mobile

    Categories

    EEO Report

    FCC Public File

    FCC Applications


    Follow @1350kman on Twitter · Manhattan Broadcasting Company is an equal opportunity employer.
    Manhattan Broadcasting does not discriminate in sale of advertising on the basis of race, gender, or ethnicity, and will not accept advertising which does so discriminate. © 2024 Manhattan Broadcasting Company.

    Follow @1350kman on Twitter · Manhattan Broadcasting Company is an equal opportunity employer.
    Manhattan Broadcasting does not discriminate in sale of advertising on the basis of race, gender, or ethnicity, and will not accept advertising which does so discriminate. © 2024 Manhattan Broadcasting Company.

    Type above and press Enter to search. Press Esc to cancel.

    x